Roadwork Improvements UPDATE: The city's contractor, Pawtucket Hot Mix Asphalt Inc.(PHMA), has scheduled paving in the Interlocken Road neighborhood on Tuesday, Oct. 15. The contractor will be reclaiming and grading Byron Avenue on Tuesday, Oct. 15. Tenth Street will be reclaimed on Wednesday, Oct. 16 or Thursday, Oct. 17. Structures will be adjusted on Roger Williams Avenue the week of Oct. 14.
During construction the roads may be closed, except to local traffic. Motor vehicle access to residents' properties may be limited or restricted for brief periods of time during construction. The hours of construction will typically be from 7 a.m. until 5 p.m. Monday through Friday, although longer hours and weekend work may be required to complete the project in a timely manner. Temporary “NO PARKING” signs will be posted along these roads and will be enforced during the hours of construction. Parking will be permitted outside of construction hours.